Managing dredge projects to minimise environmental impacts is an issue found internationally. A large dredging operation of our client, Rohde Nielsen A/S – for New Zealand’s largest port of Tauranga – required strict limits on the turbidity during channel works. DHI worked with Rohde Nielsen A/S to provide a tool which estimated the turbidity level expected in the surroundings for any given dredge scenario with a combination of other dredging activities. This allowed operators to plan and execute dredging scenarios to estimate environmental impacts with more certainty.

Challenge

Our client was required to meet specific turbidity consent limits to ensure that the harbour maintains environmental standards for recreation and tourism. They required a resource for carrying out optimal project planning and considering dredge scenarios with expected turbidity levels within acceptable values. All within a tight deadline.


Solution

Rohde Nielsen A/S worked with DHI swiftly to produce a web-based tool that was useful to their existing project. The Marine Impact Advisor Tool significantly contributed to the overall success of the dredging project.

Solution highlights:

  • Rapid assessment of environmental impacts based on predefined conditions

  • Only requires a relatively low web server load

  • Extremely informative inputs allow for optimal sequencing of dredging works, with the environment as the key element

  • Effectively minimises the impact of the dredge operations on turbidity levels

Results

More certain assessment

of environmental impacts of the dredging operation

Reduction in turbidity levels

after having fulfilled consent limits requirements

Operational savings

made for happy clients who had more time due to minimising breaches of turbidity levels


‘The scope of work was executed on time, in full compliance with the turbidity consent limits on all three trigger levels and to the fullest satisfaction of all stakeholders.’

Ingolf Gudjonsson
Project Manager
Rohde Nielsen A/S



Mount Maunganui and southern entrance to Tauranga Harbour with the dredging equipment involved in the dredging works. © DHI

The full story

Challenge

The project for the client, Rohde Nielsen A/S (RN), involved the deepening and widening of shipping channels from 12.9 meters to 14.5 meters depth inside the harbour and 15.8 meters outside the harbour. Environmental aspects were a key element for the project.

The dredging was the final building block in a NZD 350 million capital expenditure program over a period of five years, completed in 2016. The dredging project, at a cost of NZD 50 million, upon completion allows New Zealand’s exporters and importers to access the savings for larger ships. It also allows for the Port of Tauranga to host giant cruise ships, such as the Ovation of the Seas, which docked in Tauranga on its maiden voyage to New Zealand in the summer of 2016/2017.

The client’s pain stemmed from a turbidity issue in this channel dredging.

Bathymetry of Tauranga Harbour showing depths relative to mean sea level. © DHI


RN was aware of turbidity issues that had occurred during a previous capital dredging campaign and wanted to minimise this reoccurring. Stakeholders of the harbour expected the continuation of high integrity in the harbour, despite port operations and especially in light of the high use of the area for recreational activities in the summer months.

Maintenance dredging can be excessively expensive when using conventional methods and the client was looking for a way to assess the turbidity.

The Dredging Environmental Management Plan for the project set out limits on turbidity at six key monitoring locations inside the harbour, measuring real-time turbidity. These limits were used to trigger level 1 or level 2 management responses and also set absolute environmental limits that were not to be exceeded during the dredging operation.


Solution

Part of the Dredging Environmental Management Plan was the development of a Marine Impact Advisor Tool. This tool provided Rohde Nielsen with a web-based system that could deliver dredge spill model results for a particular user-defined dredging regime and pre-defined hydrodynamic conditions.

Calibration of the sediment transport model for a period of extended dry weather and calm wind conditions. © DHI

Based on an analysis of field data sediments, which included clay, fine silt, medium silt, coarse silt and fine sand, the portal allows the user to define the following via a user-friendly interface:

  • Dredge location (including dual dredge option)

  • Hydrodynamic condition (tide and wind)

  • Type of sediment to be dredged

  • Timing of spill (continuous or relative to tide)

  • Type of dredging equipment

  • Production rate and assumed portion of sediment type at the dredge site

The hydrodynamic tool used for these determinations was MIKE Powered by DHI’s MIKE 21 with a flexible mesh component. Bathymetry was derived from a combination of the latest Port of Tauranga survey data, LiDAR and most recent chart data – and was calibrated against available water level and current meter data.

Once the spill scenario was specified, the Marine Impact Advisor Tool used the information to populate a MIKE 21 Sediment Transport setup file on a web server and a sediment transport model is run for either a 2- or 14-day period, as specified by the user.

Such an approach allowed the client to rapidly determine the likely envelop of turbidity levels that could occur for any given user-defined dredging regime in the context of the allowable environmental limits.


Results

Meeting the turbidity consent limits was considered as the most important challenge of the project. This was achieved. RN managed the project planning with dredge scenarios based on models with turbidity levels within acceptable levels.

RN successfully managed to complete the one-year dredging contract well within budget and time without a single breach of turbidity response level. The works were executed on time, in full compliance with the defined turbidity limits on all three-trigger levels and to the fullest satisfaction of all stakeholders.

Information provided by the Marine Impact Advisor Tool along with in-situ measurements of dredge material, frequent reporting on dredge volumes and online monitoring of turbidity at key sites in the harbour all became part of the adaptive management approach carried out during the execution of the works.

About the client

RN is a privately owned global marine dredging contractor. Operating from Denmark, the company owns and operates a fleet of 43 specialised dredging units, moving annually some twenty five million cubic meters of material.

RN ranks number ten in a listing of the largest dredging companies in the world. It ranks number five in the listing of globally operating dredging companies. Learn more about RN here.


Software used

The Marine Impact Advisor Tool, which uses components of MIKE 21

Case story - Highlights flyer

Estimate your dredging impacts with more certainty

Let us help

Want to take the next step in solving your challenge?

Contact us